The Challenge​

Bridge construction formed part of the road construction requirement, helping to shorten travel
distance for drivers. Design requirements included:

• Life load according to EN 1991

• A cover depth of 1.15 metres

• Backfilling parameters according to SDM with sub-base material

• 120 years’ durability

• Corrosion protection layers: zinc coating of thickness according to EN ISO 1461:2009 Fe/Zn 115, surface of the structure painted 100% on both sides with paint to thickness of 300 μm

The Solution

ViaCon Sweden met the challenge, providing UltraCor Special 38U, contributing to the successful construction of the bridge by August 2019. The resulting steel structure had the following measurements:

Span: 14.42 m
Rise: 4.13 m
Bottom length: 12.3 m
Top length: 12.3 m
Plate thickness: 9 mm
Steel grade: S420MC
Sweden

Stakeholders

Investor: Trafikverket

Designer
: WSP

Product: UltraCor Special 38U

Contractor: PEAB

The Advantage

With ViaCon, the new six-kilometer-long road including the new bridge shortened travel distance, leading to increased safety as well as other short and long-term environmental performance benefits, such as.

•Easier and faster to build, due to simpler structure

•Lower maintenance requirements

•Competitive costs, including less energy and fossil fuel consumption during construction

•Steel is 100% recyclable, contributing to the circular economy at end of life